Boulevard du Souverain 100, 1170 Bruxelles
OOEB EMPEREUR - Boulevard de l'Empereur 5
STATUS REPORT – December 5, 2023
DISTRIBUTION
Name | Initials | Function | Reception |
Anthony Anderson | AAN | Maître d’ouvrage | x |
Edouard Dirven | EDR | Maître d’ouvrage | x |
PHICAP | |||
Etienne Bruant | EBR | Director | x |
Bart Van Haesendonck | BVH | Manager | x |
Valérie Fauqueux | VFA | Project Manager | x |
Phase status
Phase
|
Completion
|
---|
Task list
Creation date
|
List
|
Action
|
Details
|
Status
|
Stakeholder Role
|
---|---|---|---|---|---|
Contracts
|
|||||
2023-11-22
|
Admin/documents
|
For Info
|
15/11/2023 - Return of signed purchase order for the special techniques design office - GEI (represented by Nicolas Bodson)
|
Done
|
Eng. Consultants
|
2023-11-22
|
Admin/documents
|
For Info
|
15/11/2023 - Return of the purchase order signed for Smart Ceiling - Interalu (represented by Kurt Van Looveren)
|
Done
|
Contractor
|
2023-11-22
|
Admin/documents
|
For Info
|
15/11/2023 - Return of purchase order signed for HVAC works - VLC Construct. (represented by Cliff Van Lierde)
|
Done
|
Contractor
|
2023-11-22
|
Admin/documents
|
For Info
|
15/11/2023 - Return of purchase order signed for Electricity works - VLC Construct. (represented by Cliff Van Lierde)
|
Done
|
Contractor
|
2023-11-22
|
Admin/documents
|
For Info
|
06/11/2023 - Return of signed purchase order for stability consultancy - GEI (represented by Valérie Anne Delvaux)
|
Done
|
Structural Eng.
|
2023-11-22
|
Admin/documents
|
For Info
|
06/11/2023 - Return of signed purchase order for PEB - T4M consultancy (represented by Philippe Baudin)
|
Done
|
MEP Eng.
|
2023-11-22
|
Follow-up contract
|
To Precise
|
Architect agreement adapted according to comments - currently being validated by the architect before being sent to owner for signature
|
In progress
|
Architect
|
Finance
|
|||||
2023-11-22
|
Business plan
|
For Info
|
Works before 01/10/2023 :
- Shake / entrance hall rénovation : 141.490,29 € - Démolition works : 53.150,00 € - Asbestos removal : 50.400,00 € - Phicap Investment fees : 36.000,00 € TOTAL : 281.040,29 € |
Done
|
PM Dev
|
2023-11-22
|
Business plan
|
For Info
|
Order VLC as from 01/10/2023 :
- HVAC : 556.557,85 € - Electricity : 85.795,80 € - Chape : 45.792,70 € (pending asbestos removal) - Completion works : 520.000,00 € (estimate - pending offer) - EV chargers : 27.866,51 € - Entrance door : 9.441,87 € - Schedule of condition : 550,00 € TOTAL : 1.246.004,73 € |
Done
|
Contractor
|
2023-11-22
|
Business plan
|
For Info
|
Interalu - Smart Ceiling :
- 150.000,00 € (estimate - offer as from 121.773,00€ confirmed by Interalu + lighting estimate) |
Done
|
Contractor
|
2023-11-22
|
Business plan
|
For Info
|
EPC Certification by T4M :
- 2.275,00 € |
Done
|
Eng. Consultants
|
2023-11-22
|
Business plan
|
For Info
|
Architect :
- 15.660,00 € |
Done
|
Architect
|
2023-11-22
|
Business plan
|
For Info
|
Engineering :
- 17.447,50 € |
Done
|
Structural Eng.
MEP Eng.
|
2023-11-22
|
Business plan
|
For Info
|
Health & Security :
- 990,00 € |
Done
|
Other
|
2023-11-22
|
Business plan
|
For Info
|
Project management :
- 85.103,10 € |
Done
|
PM Dev
|
2023-11-22
|
Business plan
|
For Info
|
TOTAL GENERAL :
- 1.798.520,62 € Excl. VAT |
To follow
|
PM Dev
|
2023-11-22
|
Cost control
|
To Approve
|
Received on 20/11/2023 - Tender (out of request for tender completion) for frames as described in the initial call for tender :
- 133,492.60 €, including screens and acoustic glazing |
To follow
|
Contractor
|
Timeline
|
|||||
2023-11-22
|
General timeline
|
To Precise
|
Restart of work following shutdown due to discovery of asbestos on 27/11/2023. Contractor to review schedule to start HVAC work pending asbestos removal authorisations.
|
In progress
|
PM Dev
|
2023-11-22
|
General timeline
|
To Precise
|
JANUARY 2024 - Completion of HVAC, electrical and smart ceiling works
|
To follow
|
PM Dev
|
2023-11-22
|
General timeline
|
To Precise
|
FEBRUARY 2024 - End of work of special techniques and completion work (windows, insulation, sanitary facilities, ... etc.)
|
To follow
|
PM Dev
|
2023-11-22
|
General timeline
|
To Precise
|
MARCH 2024 - Provisional acceptance of works
|
To follow
|
PM Dev
|
2023-11-22
|
Detailed timeline
|
For Info
|
All weekly site meetings take place on Fridays from 9.30 am, on site - Boulevard de l'Empereur 5, 1000 Brussels.
|
Done
|
PM Dev
|
Permits
|
|||||
2023-11-21
|
Delivery
|
For Info
|
Licence issued on 16/11/2023
|
Done
|
Authority
|
2023-11-21
|
Introduction
|
For Info
|
First licence application (without architect) submitted on 17/08/2022
|
Done
|
PM Dev
|
2023-11-22
|
Introduction
|
For Info
|
Second planning application (with architect) submitted on 09/03/2023
|
Done
|
Architect
|
2023-11-22
|
Follow-up
|
For Info
|
Concertation Commission on 06/06/2023 and favourable opinion subject to :
- Unify the volume and architectural treatment of existing and planned technical sheds in the continuity of facades (colour); |
Done
|
Architect
|
2023-11-22
|
Follow-up
|
For Info
|
Additional plans submitted to Commune on 04/09/2023, following the Consultation Committee meeting
|
Done
|
PM Dev
|
Tendering
|
|||||
2023-11-22
|
Tendering file
|
For Info
|
21/04/2023 - Final report on the analysis of the HVAC and Electrical tenders by the GEI consultancy firm
|
Done
|
PM Dev
|
2023-11-22
|
Tendering file
|
For Info
|
05/06/2023 - AAN sends recommendations to EdR indicating VLC as contractor for HVAC and electrical work
|
Done
|
PM Dev
|
2023-11-22
|
Tendering file
|
For Info
|
29/08/2023 - Client agreement indicating that VLC can carry out the HVAC and electrical work -> Budget validated at €1,994,347.00 inc VAT (including renovation of the entrance + demolition + asbestos removal)
|
Done
|
Client
|
2023-11-22
|
Tendering file
|
For Info
|
19/10/2023 - First version of call for tenders for completion sent to VLC for information
|
Done
|
Contractor
|
2023-11-22
|
Tendering file
|
To Produce
|
25/10/2023 - Following an analysis on construction site, the updated call for tenders for completion of work is sent to VLC Construct.
|
In progress
|
Contractor
|
Works
|
|||||
2023-11-22
|
Construction site
|
For Info
|
03/08/2023 - Coordination meeting with VLC, AAN and PM Phicap,
|
Done
|
PM Dev
|
2023-11-22
|
Construction site
|
For Info
|
18/09/2023 -> First site coordination meeting - "kick off" with all participants
|
Done
|
PM Dev
|
2023-11-22
|
Construction site
|
For Info
|
17/10/2023 - Pre-works survey carried out by an expert
|
Done
|
Contractor
|
2023-11-22
|
Construction site
|
For Info
|
GENERAL - A list of technical execution sheets, managed by PM, circulates between contractors and design technical offices for regular monitoring of validation and/or comments - Last updated on 17/11/2023
|
In progress
|
PM Dev
|
2023-11-22
|
Construction site
|
For Info
|
Between 23/10 and 02/11 - Demolition of screeds on levels +3 and +4
|
Pending
|
Contractor
|
2023-11-22
|
Construction site
|
For Info
|
20/10/2023 - Dismantling, demolition and removal of radiators and ventilation cassettes on levels +3 and +4
|
|
Contractor
|
2023-11-22
|
Construction site
|
To Demand
|
20/10/2023 - Les câblages de tout l'étage aboutissent à un seul tableau dans le local technique de la zone entrée. PM demande s'il faut prévoir un tableau divisionnaire spécifique par partie privative des plateaux
|
In progress
|
PM Dev
|
2023-11-22
|
Construction site
|
To Analyse
|
27/10/2023 - During screed demolition tests, contractor discovered asbestos plates protecting drowned cables in the screed. STOPPING WORKS for an asbestos diagnostic, authorization request and asbestos removal supply
|
|
Contractor
|
2023-11-22
|
Construction site
|
To Organize
|
17/11/2023 - OK for asbestos diagnostic : presence of cabling protection in a narrow, limited area along façades over a width of +/- 20 cm - Awaiting demolition tender and authorisation
|
In progress
|
Contractor
|
2023-11-22
|
Construction site
|
For Info
|
17/11/2023 - RESTART OF WORK on 27/11/2023 for special techniques. The asbestos removal and screed demolition work will follow (asbestos removal authorisation deadline).
|
In progress
|
Contractor
|
2023-11-22
|
Construction site
|
For Info
|
17/11/2023 - Launch of the chassis order (to be taken from completion batch), taking into account the 12 weeks announced for production.
|
In progress
|
Contractor
|