OOEB EMPEREUR - Boulevard de l'Empereur 5

STATUS REPORT – December 5, 2023


DISTRIBUTION

Name Initials Function Reception
Anthony Anderson AAN Maître d’ouvrage x
Edouard Dirven EDR Maître d’ouvrage x
PHICAP
Etienne Bruant EBR Director x
Bart Van Haesendonck BVH Manager x
Valérie Fauqueux VFA Project Manager x

 

Phase status

Phase
Completion

Task list

Creation date
List
Action
Details
Status
Stakeholder Role
Contracts
2023-11-22
Admin/documents
For Info
15/11/2023 - Return of signed purchase order for the special techniques design office - GEI (represented by Nicolas Bodson)
Done
Eng. Consultants
2023-11-22
Admin/documents
For Info
15/11/2023 - Return of the purchase order signed for Smart Ceiling - Interalu (represented by Kurt Van Looveren)
Done
Contractor
2023-11-22
Admin/documents
For Info
15/11/2023 - Return of purchase order signed for HVAC works - VLC Construct. (represented by Cliff Van Lierde)
Done
Contractor
2023-11-22
Admin/documents
For Info
15/11/2023 - Return of purchase order signed for Electricity works - VLC Construct. (represented by Cliff Van Lierde)
Done
Contractor
2023-11-22
Admin/documents
For Info
06/11/2023 - Return of signed purchase order for stability consultancy - GEI (represented by Valérie Anne Delvaux)
Done
Structural Eng.
2023-11-22
Admin/documents
For Info
06/11/2023 - Return of signed purchase order for PEB - T4M consultancy (represented by Philippe Baudin)
Done
MEP Eng.
2023-11-22
Follow-up contract
To Precise
Architect agreement adapted according to comments - currently being validated by the architect before being sent to owner for signature
In progress
Architect
Finance
2023-11-22
Business plan
For Info
Works before 01/10/2023 :
- Shake / entrance hall rénovation : 141.490,29 €
- Démolition works : 53.150,00 €
- Asbestos removal : 50.400,00 €
- Phicap Investment fees : 36.000,00 €

TOTAL : 281.040,29 €
Done
PM Dev
2023-11-22
Business plan
For Info
Order VLC as from 01/10/2023 :
- HVAC : 556.557,85 €
- Electricity : 85.795,80 €
- Chape : 45.792,70 € (pending asbestos removal)
- Completion works : 520.000,00 € (estimate - pending offer)
- EV chargers : 27.866,51 €
- Entrance door : 9.441,87 €
- Schedule of condition : 550,00 €

TOTAL : 1.246.004,73 €
Done
Contractor
2023-11-22
Business plan
For Info
Interalu - Smart Ceiling :
- 150.000,00 € (estimate - offer as from 121.773,00€ confirmed by Interalu + lighting estimate)
Done
Contractor
2023-11-22
Business plan
For Info
EPC Certification by T4M :
- 2.275,00 €
Done
Eng. Consultants
2023-11-22
Business plan
For Info
Architect :
- 15.660,00 €
Done
Architect
2023-11-22
Business plan
For Info
Engineering :
- 17.447,50 €
Done
Structural Eng. MEP Eng.
2023-11-22
Business plan
For Info
Health & Security :
- 990,00 €
Done
Other
2023-11-22
Business plan
For Info
Project management :
- 85.103,10 €
Done
PM Dev
2023-11-22
Business plan
For Info
TOTAL GENERAL :
- 1.798.520,62 € Excl. VAT
To follow
PM Dev
2023-11-22
Cost control
To Approve
Received on 20/11/2023 - Tender (out of request for tender completion) for frames as described in the initial call for tender :
- 133,492.60 €, including screens and acoustic glazing
To follow
Contractor
Timeline
2023-11-22
General timeline
To Precise
Restart of work following shutdown due to discovery of asbestos on 27/11/2023. Contractor to review schedule to start HVAC work pending asbestos removal authorisations.
In progress
PM Dev
2023-11-22
General timeline
To Precise
JANUARY 2024 - Completion of HVAC, electrical and smart ceiling works
To follow
PM Dev
2023-11-22
General timeline
To Precise
FEBRUARY 2024 - End of work of special techniques and completion work (windows, insulation, sanitary facilities, ... etc.)
To follow
PM Dev
2023-11-22
General timeline
To Precise
MARCH 2024 - Provisional acceptance of works
To follow
PM Dev
2023-11-22
Detailed timeline
For Info
All weekly site meetings take place on Fridays from 9.30 am, on site - Boulevard de l'Empereur 5, 1000 Brussels.
Done
PM Dev
Permits
2023-11-21
Delivery
For Info
Licence issued on 16/11/2023
Done
Authority
2023-11-21
Introduction
For Info
First licence application (without architect) submitted on 17/08/2022
Done
PM Dev
2023-11-22
Introduction
For Info
Second planning application (with architect) submitted on 09/03/2023
Done
Architect
2023-11-22
Follow-up
For Info
Concertation Commission on 06/06/2023 and favourable opinion subject to :
- Unify the volume and architectural treatment of existing and planned technical sheds in the continuity of facades (colour);
Done
Architect
2023-11-22
Follow-up
For Info
Additional plans submitted to Commune on 04/09/2023, following the Consultation Committee meeting
Done
PM Dev
Tendering
2023-11-22
Tendering file
For Info
21/04/2023 - Final report on the analysis of the HVAC and Electrical tenders by the GEI consultancy firm
Done
PM Dev
2023-11-22
Tendering file
For Info
05/06/2023 - AAN sends recommendations to EdR indicating VLC as contractor for HVAC and electrical work
Done
PM Dev
2023-11-22
Tendering file
For Info
29/08/2023 - Client agreement indicating that VLC can carry out the HVAC and electrical work -> Budget validated at €1,994,347.00 inc VAT (including renovation of the entrance + demolition + asbestos removal)
Done
Client
2023-11-22
Tendering file
For Info
19/10/2023 - First version of call for tenders for completion sent to VLC for information
Done
Contractor
2023-11-22
Tendering file
To Produce
25/10/2023 - Following an analysis on construction site, the updated call for tenders for completion of work is sent to VLC Construct.
In progress
Contractor
Works
2023-11-22
Construction site
For Info
03/08/2023 - Coordination meeting with VLC, AAN and PM Phicap,
Done
PM Dev
2023-11-22
Construction site
For Info
18/09/2023 -> First site coordination meeting - "kick off" with all participants
Done
PM Dev
2023-11-22
Construction site
For Info
17/10/2023 - Pre-works survey carried out by an expert
Done
Contractor
2023-11-22
Construction site
For Info
GENERAL - A list of technical execution sheets, managed by PM, circulates between contractors and design technical offices for regular monitoring of validation and/or comments - Last updated on 17/11/2023
In progress
PM Dev
2023-11-22
Construction site
For Info
Between 23/10 and 02/11 - Demolition of screeds on levels +3 and +4
Pending
Contractor
2023-11-22
Construction site
For Info
20/10/2023 - Dismantling, demolition and removal of radiators and ventilation cassettes on levels +3 and +4
Contractor
2023-11-22
Construction site
To Demand
20/10/2023 - Les câblages de tout l'étage aboutissent à un seul tableau dans le local technique de la zone entrée. PM demande s'il faut prévoir un tableau divisionnaire spécifique par partie privative des plateaux
In progress
PM Dev
2023-11-22
Construction site
To Analyse
27/10/2023 - During screed demolition tests, contractor discovered asbestos plates protecting drowned cables in the screed. STOPPING WORKS for an asbestos diagnostic, authorization request and asbestos removal supply
Contractor
2023-11-22
Construction site
To Organize
17/11/2023 - OK for asbestos diagnostic : presence of cabling protection in a narrow, limited area along façades over a width of +/- 20 cm - Awaiting demolition tender and authorisation
In progress
Contractor
2023-11-22
Construction site
For Info
17/11/2023 - RESTART OF WORK on 27/11/2023 for special techniques. The asbestos removal and screed demolition work will follow (asbestos removal authorisation deadline).
In progress
Contractor
2023-11-22
Construction site
For Info
17/11/2023 - Launch of the chassis order (to be taken from completion batch), taking into account the 12 weeks announced for production.
In progress
Contractor
Confidential information